2
Business days required wait
20
Days ticket is valid

About Indiana 811

Indiana 811 serves all of Indiana with online and phone ticket submission. Indiana's mix of urban centers and agricultural areas creates diverse underground infrastructure across the state.

Submit tickets at https://indiana811.org or dial 811.

Required Wait Period

Indiana requires 2 full business days notice before excavation. The ticket clock starts when Indiana 811 confirms receipt of the ticket.

Use the Wait Time Calculator to find your exact dig date.

Ticket Validity & Re-Notify

Indiana's 20-day validity window is moderate for the Midwest. Projects extending beyond 17 days will need re-notification.

Private Lines in Indiana

Indiana has significant agricultural private utility infrastructure and rural propane service lines, particularly in central and northern Indiana.

Full guide: What 811 Does NOT Cover.

⚡

Calculate Your Indiana Dig Date

Get your exact legal dig date, expiration, and re-notify reminder.

Open Calculator

Related Guides

📞

How 811 Works

Complete process guide.

🎨

Color Codes

What the marks mean.

🔄

Re-Notify Rules

Ticket expired mid-project?

â„šī¸ Disclaimer Indiana 811 rules subject to change. Verify with Indiana 811 before digging.