3
Business days required wait
15
Days ticket is valid

About Miss Utility (Virginia)

Miss Utility serves Virginia as part of the broader Miss Utility system covering the Mid-Atlantic region. Virginia has dense Northern Virginia suburban utility corridors, significant agricultural infrastructure in the Shenandoah Valley, and coastal utility considerations in Hampton Roads.

Submit tickets at https://www.missutility.net or dial 811 from any phone.

Required Wait Period in Virginia

Virginia requires 3 business days notice before excavation. Miss Utility offers online ticket submission through their portal and serves Virginia as part of a regional system covering MD, DE, DC, and parts of WV.

Use the Wait Time Calculator to find your exact dig date accounting for weekends and holidays.

Ticket Validity and Re-Notify in Virginia

Virginia's 15-day validity window is shorter than many Southern states. For any Virginia project running longer than 12 days, re-notification is required. Miss Utility's online system handles this efficiently.

⚠ Short Validity Window 15-day tickets are short. Plan re-notifications proactively.

Private Lines in Virginia

Virginia has extensive rural private well water and propane infrastructure, particularly in the Shenandoah Valley and Southwest Virginia. Northern Virginia suburban areas have dense private irrigation systems.

See the full guide: What 811 Does NOT Cover.

How to Submit a Ticket in Virginia

  1. Pre-mark excavation area in white

    Mark each planned dig location with white paint or stakes before submitting.

  2. Submit online or call 811

    Visit https://www.missutility.net or dial 811. Include address, work type, start date, and depth.

  3. Wait 3 full business days

    Do not dig until the wait period has elapsed AND all utilities have responded.

  4. Verify all responses

    Log in with your confirmation number. Every utility must show "marked" or "clear."

Calculate Your Virginia Dig Date

Get your exact legal dig date, expiration date, and re-notify reminder instantly.

Open Calculator

Related Guides

📞

How 811 Works

Complete process guide.

🎨

Color Codes

What the marks in your yard mean.

🔄

Re-Notify Rules

When your ticket expires mid-project.

ℹ️ Disclaimer Virginia 811 rules are subject to change. Always verify with Miss Utility (Virginia) before digging.